A great way to add value to your industrial building: Cut in more loading doors!
For +/- $30k per position, you can dramatically increase your property’s value to the market.
You need to account for architectural and structural design, demolition, vertical and horizontal steel supports, roll up doors, and dock equipment for starters.
You’ll need to consider where your internal electrical panels and fire risers are to look for obstructions and physical constraints.
While the work might only take 4-6 weeks, permitting is the real challenge right now. Budget an extra 30 days to get through the city.
Lastly, ask how many times your contractor has done this type of work. Not all are the same and you’ll notice a stark contrast when you find the right contractor.