Renew or Relocate Library

Should You Consolidate Two Warehouses Into One?

By Justin Smith | Smith Industrial Partners | Lee & Associates
Reviewed October 11, 2026

Consolidate warehouses when the combined operating plan improves cost, capacity, or service enough to justify the transition and the concentration of activity. Compare it with improving the existing network and with giving the buildings different roles. Reducing the number of addresses is not, by itself, an operating benefit.

A distribution network can become a record of past decisions. The original warehouse served the business well. Overflow space solved a capacity problem. An acquisition added another location. Each decision had a reason, but the combined network may never have been evaluated as a whole.

Consolidation is worth testing when those facilities duplicate work or make the company move inventory between buildings unnecessarily. It is not automatically the answer. Two sites with distinct operating roles can outperform one larger facility.

Define what each building does

Before comparing rents, identify the role of each location. Is it import receiving, bulk storage, local replenishment, returns, manufacturing support, or customer fulfillment? Which customers depend on it, and what would change if it disappeared?

A coastal fulfillment site serving time-sensitive orders has a different purpose from an inland reserve storage operation. Treating both as interchangeable square footage can produce an inexpensive network that misses its service commitments.

Test three alternatives

AlternativePotential benefitMain question to resolve
Keep the current network and improve itAvoid a major transition while correcting processesCan the existing facilities perform better without changing the footprint?
Consolidate into one facilityReduce duplicated resources and interfacility handlingDo the savings survive changes in freight, labor, service, and transition cost?
Give two facilities distinct rolesPlace inventory and activities closer to where they are neededIs the added coordination justified by service and cost advantages?

Use actual shipment origins and destinations, order characteristics, inventory requirements, and labor assumptions. Do not assume that every duplicate resource disappears or that safety stock falls in direct proportion to the number of buildings removed.

Separate recurring savings from the cost of change

Consider a hypothetical consolidation that reduces annual occupancy costs by $300,000 and interfacility transfers by $250,000. Suppose it adds $200,000 in outbound transportation and $100,000 in labor cost. Recurring net savings are $250,000 a year.

If the additional one-time investment to consolidate, after supported offsets and necessary stay costs, is $1 million, simple payback is four years before discounting or other changes. If demand weakens, costs rise, or implementation takes longer, that result changes. The proposal needs to remain sensible beyond the most favorable case.

Then test service. What happens to order cutoff times? Can receiving, replenishment, and shipping all function during peak periods? What is the contingency if the consolidated site becomes unavailable? Concentrating activity may reduce some costs while increasing the consequences of a disruption.

Use the lease calendar without letting it dictate the network

Aligned expirations can make a redesign easier. Misaligned expirations create costs that need to be priced, including overlap, transfer obligations, or an interim facility.

Build the target operating network first, then evaluate feasible paths into it. Otherwise, the company risks selecting a long-term facility because it happens to fit the next lease deadline.

Network design is a cost and service decision, not a search for the cheapest warehouse. MIT's Supply Chain Design Lab describes network design research that includes cost, service, uncertainty, and related operating decisions. For a practitioner discussion, listen to Phil Schmidbauer on warehouse and transportation optimization.

Turn the analysis into a property requirement

If consolidation remains attractive, define the required throughput, storage, utility capacity, labor access, and service radius before looking for the larger building. A single facility needs to handle the work the old sites performed together, including periods when inbound and outbound activity compete for resources.

Have the operating team describe how performance will be tested before the old facilities are released. The transition plan should account for inventory reconciliation, customer continuity, and any capacity that must remain available during the move. These requirements help identify which properties can support the plan and which only appear to offer enough square footage.

If your company is considering consolidation, contact me. We can organize facility roles, property costs, and lease dates, then identify the alternatives that merit deeper operating analysis.